Last week, Interwest Construction Inc. (ICI) began excavation under the new Canyon Creek bridge and started removal of the existing culvert. Prior to the removal of the culvert, biologists from Peninsula Environmental Group performed fish capture and removal from this section of the creek, and ICI set up the pumped stream diversion around the work area.